TITLE: 04/03 Day Shift: 1430-2330 UTC (0730-1630 PST), all times posted in UTC
STATE of H1: Planned Engineering
OUTGOING OPERATOR: None
CURRENT ENVIRONMENT:
SEI_ENV state: MAINTENANCE
Wind: 5mph Gusts, 3mph 3min avg
Primary useism: 5.75 μm/s
Secondary useism: 1.85 μm/s
QUICK SUMMARY:
IFO is in PLANNED ENGINEERING for the VENT
Today's planned activities:
- Kim/Nellie - 2nd Cleaning HAM1
- Randy - Trailer in ISI middle gantry and crane over for fit check at HAM1 +Y
- Randy - Crane out 3IFO Flange Crate
- Randy - Ameristat HAM1 HEPI grout areas
- 5 People - Move HAM1 cleanroom into final place
- VAC - Checklist for corner vent
- VAC - Leak check corner under vent
- HAM1 +Y Door Removal
- VAC - HAM1 Remove 16" Top Flange forklift down for work
- VAC - HAM1 Top Flange guague work table side
Work safe!