RF cables for ASC REFL WFS were pulled to HAM1 flange D6. Cables need to be dressed into the ISC-R2 rack. Some electronics in ISC-R2 were moved to make room for a delay line and 2-Ch Demodulator. Delay line chassis is installed. Demodulator chassis is being assembled at CIT. Existing coaxial cables need to be tested for delay phase before being pulled out and re-terminated. At this time some patch panel work in ISC-R2 will also be done.
F. Clara, M. Pirello, T. Sanchez, D. Sigg