LHO VE
jordan.vanosky@LIGO.ORG - posted 17:14, Monday 07 April 2025 (83799)
Installation of 1000AMU RGA Assembly

Travis, Melina, Jordan

Today we were able to install the assembly for the new 1000AMU RGA. (D2300253). This is located on the Y-beam manifold near BSC8.

The assembly had been previously built in the staging building and the final 8"CF connection to the gate valve on the YBM was done. There is a temporary support stand currently attached, a more permanent support and bump protection cage will be installed later.

The assembly was helium leak checked at all joints, He dwell of ~5 seconds per joint. No He signal was seen above the HLD background ~1.7E-10 Torr-l/s.

Assembly will continue to pumpdown overnight on a turbo, then will transition to the assembly 10 l/s diode ion pump.