TITLE: 04/09 Day Shift: 1430-2330 UTC (0730-1630 PST), all times posted in UTC
STATE of H1: Planned Engineering
OUTGOING OPERATOR: None
CURRENT ENVIRONMENT:
SEI_ENV state: MAINTENANCE
Wind: 4mph Gusts, 2mph 3min avg
Primary useism: 0.01 μm/s
Secondary useism: 0.21 μm/s
QUICK SUMMARY:
Plans for today:
- JIM/MITCH - HAM1 Offload HEPI Setup, disconnect actuators (continued)
- HAM1 - ISC component (continued) (Camilla, Oli, Elenna, Rahul, TJ)
- MID Station forklift - Transport and Load in ISI de/Install fixtures, wipe down, crane into place
- BSC1 (via BSC8) - CPY work starts - crew to map beams inside at spool (Betsy, Robert, Sheila, Tony)
- Randy - Remove platforms from HAM1
- HAM1 - Remove all cables form chamber
- HAM1 CRANE/FORKLIFT - SEI Stack removal
- RANDY - Crane 3IFO Flange crate over BT to first stop West Bay for later X-Arm traverse
- HAM6 VAC - Move turbo from top to back door (continued)