Rahul, Elenna, Oli, TJ, Camilla, Jim, Betsy. WP12419
Following yesterday's work 83820, this morning we removed all remaining ISC components on HAM1. Rahul removed RM1, RM2 and the SEI 10kg weights (bolts are in foil pouches with the weights).
Everything has been placed on a rack in the HAM1 cleanroom, labeled photo attached. The beamdumps are ordered as shown, BD17 and 18 are the largest plates (BD naming convention in D1000313 v17 Cartoon). Which pan each optic is in has been added to the D1000313 googledoc along with any optic serial numbers that could be read, our current working copy of the document is attached.
After lunch, TJ removed the platforms/stairs around HAM1 and Rahul, Jim and I removed all the ISC and SUS cables. All DB-25s were stored in foil in the ISC components rack (bottom shelf) and the RF cables have been given to Fil for rework.
Adding a picture of the HAM1 table after all the components were removed.
Tagging EPO for pic.