Attached is the Trello showing what has been achieved this week and what is on the books for today. Many things started yesterday were (expectedly) not finished in 1 day so will roll to today, namely finishing feedthru (and some cable) population in the empty HAM1 chamber, and evaluating ITMY and it's reaction chain for closeout given the new CPY slight pitch change. The ISI is ~en route from the staging building to the LVEA ~today in prep for install early next week. Things seem to be on schedule with how I had them laid out in the plan, even after the Monday schedule loss due to the gnarly power outage and EE component failures which took the vent staff all day to recover from.