Reports until 18:12, Tuesday 05 November 2013
LHO General
patrick.thomas@LIGO.ORG - posted 18:12, Tuesday 05 November 2013 (8391)
Ops Summary
LN2 delivery to CP4

Cheryl V., Joe D. working on mode cleaner

08:47 Reverse osmosis service
09:22 CPB work start in North bay
10:16 Kyle R. to replace the instrument air pressure regulator at CP4's level control valve
10:38 Thomas V. testing rotation stage electronics in CER, LVEA by H1 PSL racks
11:11 Kyle R. done replacing instrument air pressure regulator
11:50 Rick S. to lab to toggle noise eater on the H1 PSL laser
12:21 Reverse osmosis service
13:21 CPB work start
13:30 Jim B., Richard M. restarting H1 PSL frontend and IO chassis
13:30 Jodi F., Apollo installing dome on BSC9
13:44 Corey G. getting parts out of test stand clean room
14:13 Hugh R. seismic leveling of ITMX with HEPI
15:16 Jeff K. restarting SUS models
15:55 CPB work done