Randy, Corey, Mitch, Richard, Jim
ISI install fixture was installed today. Like LLO, it was kind of tricky, we installed the back (-Y) stand, Randy drove the first I-beam through and we attached to the -X side of the install fixture. The +Y side of this I-beam was then hung from the crane while we grabbed the second I-beam and attached to the +X side of the -Y stand. The outer +Y stand was then brought in to support the I-beams and we took two of the outrigger legs off the middle stand and used the crane to place it as close as we could to the middle of the I-beams. The -X outrigger was re-attached and we spent some time squaring the whole assembly up to the chamber before attaching the I-beams to the middle stand. We tried to seal the chamber up as good as we can, but we don't really have covers for this step. At this point, the fixture is pretty close to where it needs to be, but we need to set the height and pull the +Y stand out of the way. Should be ready to bring the ISI into the LVea and get started with the ISI install first thing tomorrow.