TITLE: 04/17 Day Shift: 1430-2330 UTC (0730-1630 PST), all times posted in UTC
STATE of H1: Planned Engineering
INCOMING OPERATOR: None
SHIFT SUMMARY:
The Vacuum team has been hard as work removing the air from the corner station. We seem to be below 20 torr.
The SPI team has Finished putting in their pickoff inside the PSL.
The SEI team workin on HAM1 still has more work to do.
SUS team has been cleaning optics in the Mega chamber as well
Also:
19:30 Hanford site called the LHO control room to let us know that they were performing a Take Cover Drill. The Operator Core decided to go over the protocol for shutting off the HVAC system in the case that this was not a drill.
LOG:
Start Time | System | Name | Location | Lazer_Haz | Task | Time End |
---|---|---|---|---|---|---|
14:45 | FAC | Nellie & Kim | LVEA | NO | Technical Cleaning | 16:45 |
15:27 | VAC | Jordan | LVEA | N | Resuming pumpdown | 16:03 |
15:35 | FAC | Tyler | LVEA | N | Putting compass stickers on cranes | 16:47 |
15:44 | Plant Study | H Miss. cont | Mid X | N | Studying plants? | 17:11 |
15:47 | PCAL | Tony | PCAL | Yes | Transfer standard PCAL measurement | 15:57 |
15:58 | SEI | Jim | LVEA Racks | n | checking ADC cabling | 19:28 |
16:01 | FAC | Randy & Mitchel | LVEA | N | Moving equipment & machines Started ~16:09 | 18:35 |
16:10 | CDS | Dave B | Remote | N | Model & DAQ restart | 16:19 |
16:12 | SPI | Sina & Ryan S | LVEA | Yes | Installing SPI Pickoff | 19:16 |
16:13 | EE | Daniel | LVEA racks | N | Running Cabling | 21:01 |
16:14 | EE | Marc | LVEA | N | Running Cables with Daniel | 23:24 |
16:17 | SEI | Jim | LVEA HAM1 | N | Working on in air side feed throughs on HAM1 | 16:20 |
16:19 | SPI | Josh | Optics Lab & PSL | Yes | Working on Optics for SPI With Escort Jeff. | 19:16 |
16:48 | EE | Fil | LVEA | N | Cabling for HAM1 with Daniel & Marc | 23:24 |
17:02 | FAC | Kim | LVEA | n | Vacuuming in MSR | 17:32 |
17:04 | PSL | Jason | PSL | Yes | Helping out with SPI | 18:56 |
17:22 | SUS | Rahul & Ryan C | LVEA HAM6-7 | N | First contact of triple suspensions. | 18:14 |
18:09 | VAC | Janos & Jordan | HAM6 area | N | Checking Guages and Valves | 20:24 |
18:42 | Sun | Ryan C | Y arm | n | Taking a walk down Y arm. | 19:15 |
18:46 | HAM1 | Camilla | LVEA | N | Retreiving Parts. | 18:53 |
19:38 | OPS | Tony, Ibrahim, Ryan C, Oli, TJ, Ryan S, Eric | Mechanical Room | N | Hanford Radiation Emergency Drill Respons | 19:39 |
20:25 | VAC | Jordan | LVEA HAM4 | N | Setting up pump on HAM4 Annulus & Cap Inventory Checks | 22:28 |
20:39 | SPI | Ryan S, Sina, Josh | PSL | Yes | Installing SPI Pickoff | 22:00 |
20:54 | VAC | Travis & Janos | HAM4 Area | N | Vacuum pump activities | 21:59 |
21:02 | SUS | Rahul, Ryan C | LVEA HAM6 | N | cleaning Tripple SUS optics. | 22:14 |
21:07 | Saftey | Richard | LVEA | N | Safety checks | 21:24 |
21:29 | SEI | Jim | LVEA HAM1 | N | Restarting HAM 1 SEI Systems | 22:28 |
22:00 | Prop | Travis | End X &Y | N | Property inventory | 22:37 |
22:14 | SEI | Jim | CER | N | Checking SEI Config | 00:14 |