Reports until 16:44, Tuesday 22 April 2025
LHO General
ibrahim.abouelfettouh@LIGO.ORG - posted 16:44, Tuesday 22 April 2025 (84070)
OPS Day Shift Summary

TITLE: 04/22 Day Shift: 1430-2330 UTC (0730-1630 PST), all times posted in UTC
STATE of H1: Planned Engineering
INCOMING OPERATOR: None
SHIFT SUMMARY:

IFO is in PLANNED ENGINEERING for the VENT

Productive day in which the following was completed:

The Trello has been updated to reflect the changes.

LOG:

Start Time System Name Location Lazer_Haz Task Time End
14:37 FAC Kim LVEA, Optics, Vac Prep N Technical cleaning 15:35
15:05 FAC Chris, Eric MY, EY, MX, EX N Checking filters, greasing fans 18:58
15:20 VAC Jordan LVEA N Purge air checks 15:34
15:36   Camilla LVEA N Tidying up 17:26
16:04 IAS Jason, RyanC LVEA N HAM1 IAS 17:07
16:04 PSL Ryan S LVEA N Picometer cable swap 17:44
16:06 SEI Mitchell, Jim LVEA N HAM1 Work Contd. 18:50
16:37 FAC Tyler MY, MX, EY, EX, LVEA N Installing compasses on cranes 21:22
16:39 PSL Fil LVEA N Picomotor cable swap 17:30
16:56 FAC Kim LVEA N Technical cleaning 17:16
17:30 EE Fil EX N Beckhoff troubleshooting 18:35
17:32 VAC Janos LVEA N Opening GV2 18:50
17:32 VAC Gerardo LVEA N Opening GV2 18:50
17:40 VAC Travis LVEA N Opening GV2 19:18
19:16   Jeff Optics Lab N Experiment setup 20:54
20:18 VAC Travis LVEA N Rougher work 01:17
20:22 EE Marc, Daniel LVEA N TDR Measurements 22:10
21:14 PCAL Rick, Tony EX N EX Calibration measurement 00:13
21:22 EE Fil EY N BRS Work 00:22
22:48 SAF Richard' LVEA N Walkabout 00:48
23:34 VAC Janos LVEA N Walkabout 00:34