TITLE: 04/29 Day Shift: 1430-2330 UTC (0730-1630 PST), all times posted in UTC
STATE of H1: Planned Engineering
OUTGOING OPERATOR: None
CURRENT ENVIRONMENT:
SEI_ENV state: MAINTENANCE
Wind: 5mph Gusts, 3mph 3min avg
Primary useism: 0.50 μm/s
Secondary useism: 0.13 μm/s
QUICK SUMMARY:
- Some of the work today includes
- EY wind fence work
- HAM1 cable work
- Ground checks of LSC/ASC diode boxes now fully cabled
- HAM1 - RM finish SUS troubleshooting - get suspended with good TFs
- HAM1 RM1 troubleshooting ground - alog missing pin 1 ?
- VAC - HAM1 Top flange Gauge work table side
- PCAL
- HAM4/5 cable trays
- When all SUS, SEI, PSL seem in good order, transition to Laser Haz and perform 200mW lockout power into HAMs
- Model work, DAQ restart
- Clean room moves, BSC8