Displaying report 1-1 of 1.
Reports until 16:13, Thursday 01 May 2025
H1 ISC
camilla.compton@LIGO.ORG - posted 16:13, Thursday 01 May 2025 - last comment - 13:56, Friday 02 May 2025(84228)
ISC Alignment Work, Day 2 in HAM1: beam profiling in progress.

Keita, Elenna, Jennie, Betsy, Camilla, Jordan, Sheila 

Summary: All diodes now cabled correctly, the periscope is installed and septum cover off ready for starting POP beam alignment, beam profiling is in progress. 

Comments related to this report
jennifer.wright@LIGO.ORG - 13:56, Friday 02 May 2025 (84238)

beam height measurements.

Displaying report 1-1 of 1.