Reports until 16:31, Monday 05 May 2025
LHO General
ryan.short@LIGO.ORG - posted 16:31, Monday 05 May 2025 (84264)
Ops Day Shift Summary

TITLE: 05/05 Day Shift: 1430-2330 UTC (0730-1630 PST), all times posted in UTC
STATE of H1: Planned Engineering
INCOMING OPERATOR: None
SHIFT SUMMARY: HAM1 beam profiling and alignment continued today along with progress on wind fences (see alog84262 for details on that).
LOG:

Start Time System Name Location Lazer_Haz Task Time End
14:42 SEI Randy, Mitchell, Corey EY N Wind fence 15:25
14:50 FAC Ken LVEA - HAM4/5 cable trays 22:47
15:07 SAF LVEA is Laser HAZARD LVEA YES LVEA is Laser HAZARD Ongoing
15:26 VAC Gerardo LVEA - Purge air dew point measurement 15:32
15:50 FAC Kim, Nellie LVEA - Technical cleaning 16:17
16:06 SEI Corey, Randy CS, EX N Moving lifts to EX for wind fence work 16:45
16:06 ISC Elenna, Jennie LVEA YES HAM1 beam profiling 17:26
16:13 VAC Jordan, Gerardo MY N Picking up vacuum pump 16:47
16:30 FAC Nellie EX N Technical cleaning 17:20
16:45 TCS Camilla LVEA - Measuring viewport 17:02
16:46 SEI Corey, Randy, Jim, Mitchell EX N EX wind fence work 19:20
16:56 EPO Jeff +1 LVEA - Tour 17:26
17:05 ISC Betsy LVEA - Checking on HAM1 crew 17:35
17:36 ISC Camilla, Betsy LVEA - Checking cables 19:38
17:55 FAC Kim, Nellie MX N Technical cleaning 18:49
17:59 EE Jackie LVEA, EX, EY - Looking for oscilloscope 21:16
18:49 FAC Nellie EY N Technical cleaning 19:36
19:20 ISC TJ LVEA - Dropping off tools 19:39
19:23 CDS Dave EY, MY N Placing PEM electronics 20:38
20:16 SEI Corey, Randy, Jim, Mitchell EX N EX wind fence work 22:05
20:33 ISC Camilla, Betsy LVEA YES HAM1 WFS alignment 22:41
20:46 FAC Chris EX, MX, EY, MY N FAMIS checks 21:42
20:52 CDS Dave MY N PEM electronics 21:52
21:17 EE Elenna OptLab N Looking for oscilloscope 21:28
22:05 CDS Marc, Fil LVEA - HAM1 electronics checks 22:20
22:28 FIT Matt Y-arm N On a jog 22:58
22:35 VAC Jordan, Gerardo MX N Moving parts 22:57
23:16 ISC Camilla, Elenna LVEA YES HAM1 beam profiling Ongoing