H1 INS (SEI, SYS)
hugh.radkins@LIGO.ORG - posted 16:49, Saturday 09 November 2013 (8455)
Cable Baskets Removed bewteen BSC3 & BSC7

Had to pull these down to get access to the BSC3 North side actuators.  Main ground wire also disconnected.  Completely SEI subsystem fault for not carving out enough space to actually work around the HEPIs.  Baskets are on the floor nearby with hardware. These really should remain out of the way until HEPI is more completed.