Friday was a busy day!
--- PSL ISS Cable Install - Jim, Mitchel
They got the cables installed in the flange with the worst access.
--- PSL PMC recovery - Filiberto, Stefan, Sheila
Replaced PMC electronics and brought the PMC back to stable locking.
--- IMC alignment - Peter, Justin, Cheryl
Input beam from the PSL was aligned to the IMC irises. I aligned the IMC and it is flashing.
-----------------------------------
On Monday, there is still a fair amount of alignment to do in HAM2 before the PSL ISS can be installed.
1) IMC alignment check - check to see that the PSL beam is still well aligned, and flashing is good
2) Align through FI - requires aligning the beam to PR2 in HAM3
3) Reroute MC REFL as IMC TRANS
When these alignments have been completed, the PSL ISS Assembly can be installed in HAM2
-----------------------------------
IO install work to do latter in the week:
- remove, rework, and replace the PR2 scraper baffle