TITLE: 05/23 Day Shift: 1430-2330 UTC (0730-1630 PST), all times posted in UTC
STATE of H1: Planned Engineering
INCOMING OPERATOR: Ibrahim
SHIFT SUMMARY:
Commissioners continued making progress with being to align more cavities/states of H1. And the plan is to continue with more alignment work (Maybe locking tonight for Elenna & Ibrahim?).
LOG:
- Sheila sorting through H1 alignment enough to make ISCT1 alignment work better.
- 1451 Issues with POP is making this H1 alignment work tough; Sheila is now taking H1's IMC to OFFLINE
- 1511 Going on floor to see if sidebands are on. (they were not, so Sheila turned them ON)
- 1433 EX Wind Fence (mitch.randy)
- 1533 LVEA cleaning (kim, nellie)
- 1606 kim out, 1615 nellie out
- 1622 isct1 table alignment continued (sheila,tj)
- Stop when EQ arrived
- 1830 Return to alignment work (sheila, tj)
- 1706-1732 H2 room (kim,nellie)
- 1734 EQ trips several ISIs
- 1952 Setting up camera to monitor new HAM1 pump. After getting the go-ahead with Gerardo. (dave)
- 2010-2320 Continuing ISCT1 alignment (sheila, camilla)
- 2035 TCS Chassis being toggled on/off (tj)
- 2115-2147 Tour in Control Room (ibrahim)