TITLE: 05/29 Day Shift: 1430-2330 UTC (0730-1630 PST), all times posted in UTC
STATE of H1: Planned Engineering
OUTGOING OPERATOR: Tony
CURRENT ENVIRONMENT:
    SEI_ENV state: CALM
    Wind: 5mph Gusts, 3mph 3min avg
    Primary useism: 0.02 μm/s
    Secondary useism: 0.10 μm/s
QUICK SUMMARY: Still locked at PREP_ASC_FOR_FULL_IFO. HAM1 is in DAMPED, everything else looks OK.

Plan for the day is to get the ASC working.