Reports until 15:58, Tuesday 12 November 2013
H1 AOS
mitchell.robinson@LIGO.ORG - posted 15:58, Tuesday 12 November 2013 (8484)
ITMX Manifold Cryo Pump Baffle completion
Thomas V, Mitchell R
Today the newly modified lower Copper plates (for the eddy current damper) were installed. This completes the remaining installation work. Also time was spent cleaning up and re-bagging parts and tools. This will be completed tomorrow after tracking down the proper size Ameristat bags. Once clean up is complete the smaller clean room will be available for the next task.