Quarterly Functionality Test Performed on EX/MX Turbo Pumps

FAMIS tasks 31305 and 31320, WP 12682

Procedure checklist for both stations completed.  No issues were identified at this time.

MX: Scroll pump hours: 228.5
       Turbo pump hours: 140
       Crash bearings: 100%

EX: Scroll pump hours: 7155.9
       Turbo pump hours: 1108
       Crash bearings: 100%