LHO General
corey.gray@LIGO.ORG - posted 14:05, Tuesday 19 November 2013 (8618)
Ops DAY Summary

Day's Activities (from 8am-2pm, Dale covered the end of my shift)

Cleaning at EY (causing dust alarms)

Yawing the EX TMS

Frank will be heading to EX to do some electronics documentation (& possibly to EY afterward)---this should only be during the morning

Kiwamu is measuring power at H1 PSL

Kyle is soft-closing GV17 for spool/annulus work

Koji & Rich working at HAM6

First Contacting HAM3 this morning (& maybe BSC3 this afternoon)

Restarting h1omc for a new model (Dave)

Test Dust Monitor code at all locations (Patrick)

Dust Monitor #9 in the LVEA has been having status alarms throughout the day

Baling on X-arm

Insulation on Yarm (Y1)