Day's Activities (from 8am-2pm, Dale covered the end of my shift)
Cleaning at EY (causing dust alarms)
Yawing the EX TMS
Frank will be heading to EX to do some electronics documentation (& possibly to EY afterward)---this should only be during the morning
Kiwamu is measuring power at H1 PSL
Kyle is soft-closing GV17 for spool/annulus work
Koji & Rich working at HAM6
First Contacting HAM3 this morning (& maybe BSC3 this afternoon)
Restarting h1omc for a new model (Dave)
Test Dust Monitor code at all locations (Patrick)
Dust Monitor #9 in the LVEA has been having status alarms throughout the day
Baling on X-arm
Insulation on Yarm (Y1)