TITLE: 08/26 Day Shift: 1430-2330 UTC (0730-1630 PST), all times posted in UTC
STATE of H1: Observing at 152Mpc
INCOMING OPERATOR: Ibrahim
SHIFT SUMMARY:
We tried to run an Initial_ Alignment but SRC aligning didn't work because the New Whitening Chassis or cable that was installed had an issue.
NLN @ 21:14:27 UTC
Back to Observing by 21:20:06 UTC
21:52 UTC Tyler started pushing his rocks around with the tractor over at the far end of the Staging building.
22:50 UTC Tyler's tractor work has lost traction with the commissioning crew and there will be no more tractoring rocks around while locked.
LOG:
Start Time | System | Name | Location | Lazer_Haz | Task | Time End |
---|---|---|---|---|---|---|
15:03 | FAC | Erik | EY | No | Changeing Presure release valve | 15:38 |
15:04 | FAC | Randy | LVEA | N | Forklifing from LSB to OSB | 15:46 |
15:06 | VAC | Jordan | HAM Shaq | N | Gauge work in FTCE | 19:06 |
15:10 | wFAC | Chris | EY | N | Filter Checks | 16:20 |
15:14 | FAC | Kim & Nellie | LVEA | N | Technical Cleaning. | 17:44 |
15:16 | VAC | Travis & Janos | Mid Y -> Mid X | N | Getting tools from Mid Y then heading to Mid X | 23:26 |
15:17 | Richard | LVEA | N | Measure Viewport Simulator | 15:26 | |
15:22 | FAC | Tyler & Beaver Bark | Staging Bld | N | Dumping rocks from a Dump truck, & Moving gravel with tractor | 17:20 |
15:27 | FAC | Randy & Mitchel | LVEA | N | Working on Clean room | 15:46 |
15:31 | EE | Fil | LVEA HAM 6&7 | N | SUS & IOC rack cable racks | 18:56 |
15:33 | 3IFO | Tyler | LVEA & ES | N | 3 IFO checks | 16:03 |
15:37 | LN2 | NORCO | Both Mid X&Y | no | Liquid Nitrogen refill | 17:30 |
15:45 | SPI | Jeff | Optics lab | N | Dropping off parts | 15:46 |
15:45 | SUS | Rahul | End Station | N | SUS Charge measurements. | 18:26 |
15:51 | FAC | Randy | LVEA | N | Cleaning off Emod in West bay | 17:51 |
15:52 | EE | Marc | LVEA | N | Helping Fil with IOC & SUS racks | 18:56 |
16:21 | VAC | Jordan , Gerardo, Anna, Mitchel | HAM Shaq | N | FTCE Gauge work & a lil Craning, Mitchel Out early | 19:08 |
16:32 | FAC | McCarthy | LVEA | N | Joining Randy | 16:50 |
16:53 | FAC | Chris | End & Mids X&Y | N | Checking phones | 16:08 |
17:05 | FAC | Eric | HAM Shaq | N | Planning a 120V Electrical Run | 17:24 |
17:20 | PEM | SAM | LVEA + Y Arm | N | Checking accelerometers. | 17:33 |
17:24 | ISC | Keita | LVEA ISC Racks | N | Checking Cable Lengths at eh ISC racks | 18:56 |
17:25 | FAC | Nellie | EY | N | Technical Cleaning | 18:52 |
17:29 | FAC | Kim | EX | N | Technical Cleanin | 18:52 |
17:47 | FAC | Eric | EY | N | Moving an extension cord | 18:08 |
17:53 | SEI | Jim | LVEA HAM1 | N | HAM1 SEI Injections | 18:58 |
18:17 | FAC | Richard | LVEA Input arm | N | measuring the distance from the floor to Ceiling | 18:45 |
18:17 | PEM | TJ | HEPI Mezz | N | Setting up Dust Mon | 19:08 |
19:56 | ISC | Daniel | LVEA | N | Checking whitening chass for AS_C issues | 20:21 |
20:14 | ASC | Daniel | LVEA | N | Swapping ASC Whitening chassis | 20:21 |