Displaying report 1-1 of 1.
Reports until 02:38, Tuesday 09 September 2025
LHO General
ibrahim.abouelfettouh@LIGO.ORG - posted 02:38, Tuesday 09 September 2025 (86799)
OPS Eve Shift Summary

TITLE: 09/09 Eve Shift: 2330-0500 UTC (1630-2200 PST), all times posted in UTC
STATE of H1: Earthquake
INCOMING OPERATOR: Corey
SHIFT SUMMARY:

IFO is in OMC_WHITENING and LOCKING

The first 5 hours of this extended shift were quiet and well behaved. Truly the calm before the earthquake before the storm. Lockloss alog 86792.

Thanfully the next 3 hours were action packed due to 2 environmental events: a 5.8 EQ (and 4.9 aftershock) off the coast of Oregon and an electrical storm power glitch.

The Earthquake (alog 86793)

5.8 EQ from Oregon downed the IFO before SEI or SUS had a chance to prep.

The Storm (alog 86795)

The storm caused a slight power glitch that caused the high voltage for both HAM6 and the PSL to turn off.

The Aftershock:

While relocking in INITIAL_ALIGNMENT, we got an aftershock (4.9 EQ) from the same location, wich prompted EQ mode to turn on.

Initial alignment finished, I began locking, DRMI caught immediately and thanks to the awesome power of nature, this shift was not boring. Except of course, the OMC is not locking (despite turning the high voltage back on) - see below for the 3rd installment nobody asked for.

The OMC:

The OMC high voltage also tripped though I did turn it on (narrator: or so he thought)

Other:

The DARM FOM is having trouble connecting to NDS so I can't see the Violin Modes but they're extremely high (maybe due to the possbily fake measured 573 Lin Velocity of that Oregon EQ). Violin medm attached.

Anyway, I should log off now before I summon a tornado or something. Honestly, this has been a fantastic learning oppurtunity (and don't worry I have the day off tomorrow).

LOG:

Images attached to this report
Displaying report 1-1 of 1.