H1 General
ryan.crouch@LIGO.ORG - posted 16:31, Friday 26 September 2025 (87159)
OPS Monday Day shift summary

TITLE: 09/26 Day Shift: 1430-2330 UTC (0730-1630 PST), all times posted in UTC
STATE of H1: Observing at 150Mpc
INCOMING OPERATOR: TJ
SHIFT SUMMARY: We stayed locked the entire shift, 9 hours at the end of the shift. Secondary microseism is still rising.
LOG:

Start Time System Name Location Lazer_Haz Task Time End
16:48 VAC Pump LVEA N AIP pumping on HAM6 23:43
16:27 TCS Camilla VAP prep lab N Check on parts dimensions, cheeta 16:39
23:20 CAL Dripta Optics lab LOCAL PCAL checks 23:29