H1 SEI
sebastien.biscans@LIGO.ORG - posted 17:26, Tuesday 26 November 2013 - last comment - 10:38, Wednesday 27 November 2013(8752)
SEI status

Here is the current status of the aLIGO SEI work at Hanford. The main updates of this week are:

- ITMX, HAM2 and HAM3 have been tested (chambers are closed)

- HEPI generic and local models have been updated, installed and tested

 

·         BSC1 - ITMY

o    ISI + HEPI - Unlocked, Previously commissioned.

·         BSC2 - BS

o    ISI + HEPI - Unlocked, Previously commissioned.
 

·         BSC3 - ITMX

o    ISI : Testing complete, in chamber. Report validated.

o    HEPI : Unlocked.

 

·         BSC9 - ETMX

o    ISI : Unlocked. Testing complete.       

o    HEPI : Unlocked, ongoing initial alignment.

·         BSC10 - ETMY

o    ISI : Currently installed in BSC6. Will be pulled out and installed in BSC10. Payload (SUS) will be moved then. Electronics are disconnected

o    HEPI : Unlocked.

         HAM 1

o    HEPI: Locked and vented.
      Low priority testing 

·         HAM2

o   ISI: previously commissioned with HEPI locked, currently unlocked, in vacuum

o   HEPI - IPS position loops and alignment offsets installed
     Locked

·         HAM 3

o   ISI: previously commissioned with HEPI locked, currently unlocked, in vacuum

o   HEPI - IPS position loops and alignment offsets installed
     Unlocked

·         HAM 4 

o   ISI: In chamber, Previously tested during assembly validation, currently locked, no suspension installed, in-vac cables not connected.
     Electronics ready, in field cables ready, in-rack cables ready. Temporary STS cables
     Model is running, and MEDM screens are available in the Sitemap.

o   HEPI: Currently locked, to be commissioned
     Electronics ready, in field cables ready, in-rack cables ready. Temporary STS cables
     Model is running, and MEDM screens are available in the Sitemap.

·         HAM 5

o   ISI: In Chamber, Previously tested during assembly validation, currently locked, no suspension installed, in-vac cables not connected,
     Chamber temporarily closed.         
     Electronics ready, in field cables ready, in-rack cables ready. Temporary STS cables
     Model is running, and MEDM screens are available in the Sitemap.

o   HEPI: Currently locked, to be commissioned     
     Electronics ready, in field cables ready, in-rack cables ready. Temporary STS cables
     Model is running, and MEDM screens are available in the Sitemap.

·         HAM 6

o   ISI: 
     in chamber.
     Unlocked, no SUS
     Mechanical adjustments complete
     Initial in-chamber testing complete, but not validated yet

o   HEPI: Locked

 

Happy thanksgiving everybody
Comments related to this report
hugh.radkins@LIGO.ORG - 10:38, Wednesday 27 November 2013 (8760)

Corrections to Status as of 26 Nov:

BSC9--ISI is Locked

BSC10--HEPI is locked (No Payload)

HAM6--ISI Locked