Reports until 18:10, Wednesday 04 December 2013
LHO General
bubba.gateley@LIGO.ORG - posted 18:10, Wednesday 04 December 2013 (8819)
Apollo crew
Clean room was moved from BSC 6 to BSC 10, work platform disassembled at BSC 6 and reassembled around BSC 10.
Clean room then moved back over BSC 10.
E module relocated to east side of test stand clean room (only 3 bolts per leg) and in position. TIGHT FIT
West door installed on BSC 9 and bolts torqued. Only 4 bolts in dome and east door, remainder to be installed and torqued tomorrow.