TITLE: 01/15 Day Shift: 1530-0030 UTC (0730-1630 PST), all times posted in UTC
STATE of H1: Planned Engineering
INCOMING OPERATOR: None
SHIFT SUMMARY:
Update to "Status of Things": HAM1-2 Septum had a viewport cover removed (so, 3 of 4 are covered) for JAC alignment. ~100mW coming from the PSL to HAM1 for JAC (not noted on the white board).
JAC alignment work continued most of the day. Did not roll IOT2 into place (latest plans are to do this tomorrow [Fri] afternoon) with the LVEA being transitioned to SAFE prior to this work (aiming for lunchtime).
SQZ alignment work continued in the afternoon.
SUS model/daq work appears to be nearing completion (Jeff, Oli, RyanS, Dave (remote), EJ (remote)) !
LOG:
- 1541-1555 Optics Lab clean (kim)
- 1606-1712 LVEA cleaning (kim, nellie)
- 1625-1839 EY parts to LVEA (randy,mitch)
- 1710-1715 JAC work: PSL lightpipe opening for JAC, no beams out of chamber (masayuki)
- 1717-1724 Checking high voltage (masayuki)
- 1816-2053 Out to HAM1 again (masayuki)
- 1746-2126 PCal measurements (tony)
- 1755-1720 MY cleaning (nellie)
- 1756-1802 Grabbing garb (ibrahim)
- 1830-1843 pulling/inspecting a mirror mount inside HAM1 for JAC (rahul) + joined by Jason briefly
- 1844-1848 quick trip to optics lab to look for siskiyou mount (corey)
- 1835-2030 EE support for JAC (marc)
- 1902-1930 JAC (jennie, daniel)
- 1916-2053 Jason joining JAC crew with 2- LH Siskiyou Mirror Mounts!
- 1922-1950 swifting FCES (kim)
- 1927-1937 CER for cable change (oli)
- 1941 Injection work around BSC2/Beer Garden throughout the day (robert)
- 2022-2031 Heading out to HAM1 (jennie)
- 2031-2055 CER to take photo of chasis (jeff, oli)
- 2130 DAQ Restart (dave)
- 2200 JAC alignment afternoon work (masayuki, jennie)
- 2216-0000 SQZ alignment on floor & in the control room (sheila, karmeng)
- 2235-2312 Looking for cables at MY (travis)
- 2347 CER visual check (jeff)
- 0008 Word of DAQ Restarts done for the day (Dave)
- 0028 Robert heading back out for injection work near BSC2