Reports until 16:32, Thursday 15 January 2026
LHO General
corey.gray@LIGO.ORG - posted 16:32, Thursday 15 January 2026 (88769)
Thurs DAY Ops Summary

TITLE: 01/15 Day Shift: 1530-0030 UTC (0730-1630 PST), all times posted in UTC
STATE of H1: Planned Engineering
INCOMING OPERATOR: None
SHIFT SUMMARY:

Update to "Status of Things":  HAM1-2 Septum had a viewport cover removed (so, 3 of 4 are covered) for JAC alignment.  ~100mW coming from the PSL to HAM1 for JAC (not noted on the white board).

JAC alignment work continued most of the day.  Did not roll IOT2 into place (latest plans are to do this tomorrow [Fri] afternoon) with the LVEA being transitioned to SAFE prior to this work (aiming for lunchtime).  

SQZ alignment work continued in the afternoon.

SUS model/daq work appears to be nearing completion (Jeff, Oli, RyanS, Dave (remote), EJ (remote)) !
LOG: