TITLE: 02/28 Day Shift: 1530-0030 UTC (0730-1630 PST), all times posted in UTC
STATE of H1: Planned Engineering
INCOMING OPERATOR: N/A
SHIFT SUMMARY: Both doors and all viewports are now in place on HAM1 and the annulus is pumping down. Next week, after the main volume is at low enough pressure, we'll start commissioning the new JAC in with the rest of the IFO.
LOG:
| Start Time | System | Name | Location | Lazer_Haz | Task | Time End |
|---|---|---|---|---|---|---|
| 15:36 | FAC | Kim, Nellie | LVEA | N | Technical cleaning | 16:19 |
| 15:46 | FAC | Randy | LVEA | N | Prep for HAM1 door | 16:31 |
| 16:09 | VAC | Jordan | LVEA | N | Isolate turbopump on BSC8 | 16:17 |
| 16:49 | VAC | Travis | LVEA | N | HAM1 viewport and door prep | 17:34 |
| 16:50 | VAC | Jordan | LVEA | N | HAM1 viewport and door prep | 17:34 |
| 16:50 | FAC | Kim, Nellie | LVEA | N | Technical cleaning | 18:03 |
| 17:10 | SAF | Richard | LVEA | N | Checking in w/ VAC team | 17:32 |
| 17:48 | FAC | Randy | LVEA | N | Measuring cleanrooms in W-bay | 19:48 |
| 17:54 | SPI | Jeff | Opt Lab | Local | SPI fiber characterization | 20:11 |
| 17:55 | VAC | Jordan, Mitchell | LVEA | N | Prep for HAM1 cleanroom move (Mitchell out @ 18:11) | 19:27 |
| 17:57 | VAC | Betsy, Travis | LVEA | N | HAM1 door and cleanroom move (Betsy out @ 18:12) | 19:27 |
| 18:25 | TCS | Sophie, Gabriele | Prep Lab | Local | CHETA table work | 18:45 |
| 18:49 | FAC | Kim | LVEA | N | Technical cleaning | 19:35 |
| 18:51 | SAF | Richard | LVEA, CER | N | Safety checks in walls | 18:58 |
| 18:54 | TCS | Sophie | Prep Lab | Local | CHETA table work | 20:03 |
| 20:22 | SPI | Jeff, Jim | Opt Lab | Local | SPI fiber characterization (Jeff out @ 23:30) | 23:38 |
| 20:29 | FAC | Randy | LVEA | N | Craning scissor lift | 21:10 |
| 20:37 | VAC | Jordan | LVEA | N | Setting up HAM1 pump carts | 21:38 |
| 20:42 | VAC | Travis | LVEA | N | Setting up HAM1 pump carts | 21:38 |
| 22:15 | SQZ | Sheila | LVEA | N | Turning on SQZ laser | 22:45 |
| 22:45 | VAC | Travis | LVEA | N | Checking HAM1 pumps | 23:03 |
| 22:54 | TCS | Gabriele, Sophie | Prep Lab | Local | CHETA table work (Gabriele out @ 23:15) | Ongoing |
| 23:08 | JAC | Jennie, Keita | LVEA | N | Checking parts, turning off JAC heater (Keita out @ 23:40) | 00:08 |
| 00:23 | ISC | Elenna, Oli | Opt Lab | N | Assembling optics | Ongoing |