Displaying report 1-1 of 1.
Reports until 16:36, Tuesday 10 March 2026
H1 General
ryan.crouch@LIGO.ORG - posted 16:36, Tuesday 10 March 2026 (89446)
OPS Monday Day Shift Summary

TITLE: 03/10 Day Shift: 1430-2330 UTC (0730-1630 PST), all times posted in UTC
STATE of H1: Planned Engineering
INCOMING OPERATOR: Tony
SHIFT SUMMARY: Alignment work today, green arms, Xarm IR, MICH, PRX alignment is being worked on as of the end of day shift.
LOG:                                                                                                                                                                     

Start Time System Name Location Lazer_Haz Task Time End
15:09 FAC Nellie MidY N Tech clean 15:30
15:28 ALS Sheila, Camilla LVEA LOCAL ISCT beatnote alignment, Camilla turn on CO2 and SQZ lasers 16:07
15:54 FAC Kim, Nellie, Randy LVEA N Move clean room, N bay to W bay, K/N out 16:19UTC 16:42
15:56 BHD Oli Optics lab LOCAL Parts search / checks 16:26
16:09 FAC Tyler+Contractors Site N Fire inspections 20:36
16:21 EE Marc CER N Check on cables, measure video cable 17:12
16:43 FAC Randy EndY N Checks 17:13
16:52 SEI Jeff Optics lab LOCAL SPI 19:24
17:02 BHD Oli Optics lab LOCAL Helicoil HXDS alignment tooling 17:52
17:15 EE Marc Mech room N Turn on SQZ HV 17:21
17:20 FAC Eric OSB N Shut off AH 4 - offices 17:38
16:40 FAC Kim HAM Shaq N Tech clean 17:23
17:23 FAC Kim MidX N Grab supplies 17:45
17:27 TCS Sophie Prep lab N CHETA work 19:32
17:30 ISC RyanS, Jennie LVEA LOCAL HAM1 JAC table work 18:50
17:45 FAC Kim EndX N Tech clean 18:45
18:04 EE Marc LVEA LOCAL Check on JAC cable 18:18
18:39 SEI Jim LVEA, then optics N HAM6, move parts to optics lab 18:50
19:04 ICS Sheila, Jennie, RyanS LVEA HAM1 LOCAL JAC work 19:17
19:41 ISC Sheila, RyanS LVEA HAM1 N JAC table measurements 19:52
19:55 FAC Kim LVEA N Stock garb 20:28
20:27 BHD Oli Optics lab LOCAL BHSS work Ongoing
20:31 EE Marc MidY N Get cables 21:30
20:36 FAC Tyler Beamtube N Install new speed limit signs 21:36
21:00 VAC Jordan LVEA, Ybeam manifold N Anulus ion pump troubleshooting 21:48
21:28 ISC Jennie LVEA LOCAL ISCT1 table beam check 21:48
22:08 SEI Jeff Optics lab LOCAL SPI 23:12
22:17 BHD Camilla Optics lab LOCAL BHSS Ongoing
22:48 TCS Sophie Prep lab N CHETA work Ongoing
Displaying report 1-1 of 1.