elenna.capote@LIGO.ORG - posted 16:47, Friday 20 March 2026 (89583)
OMC build update for BHSS

This is a belated report of work done by me, Oli and Keita on the OMC builds for the BHSS, done yesterday March 19.

Exciting summary: build for OMCA is complete, including DCPDs and butter dish. OMCA is installed onto the BHSS platform and ready for beam alignment!

Less exciting summary: build for OMCB is halted as tombstone for DPCD A (transmission) is missing a required PCB hole for the electronic connection.

OMCA build notes:

OMCB build notes: