TITLE: 03/25 Day Shift: 1430-2330 UTC (0730-1630 PST), all times posted in UTC
STATE of H1: Planned Engineering
INCOMING OPERATOR: None
SHIFT SUMMARY: GV7 is still broken and will not hard close, HAM1 vent prep work, the PSL incursion was completed, and the BHSS work continues in the Optics lab.
LOG:
| Start Time | System | Name | Location | Lazer_Haz | Task | Time End |
|---|---|---|---|---|---|---|
| 14:15 | FAC | Kim, Nellie | LVEA | N | Tech clean | 14:54 |
| 15:05 | VAC | Gerardo, Jordan | LVEA HAM1 | N | Open ION pump | 15:09 |
| 15:08 | FAC | Randy | LVEA WBay | N | Craning Test stand, *not over the tube* | 16:12 |
| 15:19 | SEI | Jeff | Optics lab | LOCAL | Turn off laser | 15:27 |
| 15:28 | SEI | Camilla, Jeff | Optics lab | N | Parts search / checks Camilla out 15:45 | 15:48 |
| 15:35 | SEI | Jeff, Camilla | LVEA | N | Grab power meter | 15:45 |
| 16:02 | TCS | Sophie | Prep lab | N | CHETA work | 16:19 |
| 16:08 | EE | Marc, Fil | LVEA H1,2 | N | Cabling fiber, SUS to SAFE | 18:58 |
| 16:19 | Betsy | CER/Clean storage, Optics lab | N | Put away garb and other stuff | 16:37 | |
| 16:20 | BHD | Elenna, Keita | Optics lab | N | BHD/BHSS work | 17:26 |
| 16:22 | SQZ | Camilla | LVEA, SQZT7 | LOCAL/HEIGHT | SQZT7 table alignment, bringing glasses for Fil, Marc | 16:33 |
| 16:33 | PSL/SPI | Jeff, Jason, Sina | PSL, Racks, PSL encl | N / LOCAL | SPI fiber work, Jason out 18:30 | 18:46 |
| 16:39 | FAC | Kim | LVEA | N | Tech clean | 18:09 |
| 16:46 | FAC | Randy | LVEA WBay | N | Test stand work | 17:39 |
| 16:48 | ISC | Ibrahim | CER/ Clean storage | N | Inventory C3 covers | 19:21 |
| 16:48 | SQZ | Camilla, Sheila | LVEA | LOCAL | SQZT7 work, LOCAL and HEIGHT LASER HAZARD | 17:04 |
| 16:59 | ISC | Jenne | LVEA | N | Talk to Camilla/Sheila | 17:02 |
| 17:06 | BHD | Oli | Optics lab | N | BHD/BHSS work | 17:40 |
| 17:17 | ISC | Jennie | Optics lab ->LVEA | N | Check for parts, put away in LVEA | 17:35 |
| 18:23 | SPI | Bram | LVEA | N | Check with Jeff out with Jeff | 19:11 |
| 18:35 | VAC | Travis | Site | N | VAC property inventory | 21:53 |
| 18:37 | VAC | Gerardo | LVEA | N | Turn on purge air for HAM1 | 19:13 |
| 18:39 | OPS | Betsy, Tony | LVEA | N | Double checking LASER SAFE status | 19:11 |
| 19:17 | OPS | Tony | LVEA | N | Grab paper and table keys | 19:22 |
| 19:29 | FAC | Randy, Jim | LVEA | N | Turn on HAM1 CR and work on the test stand Jim out 20:20 | 20:27 |
| 19:34 | ICS | Camilla, Calum | Optics lab | N | Check on parts | 19:52 |
| 20:09 | SEI | Jeff, Bram, Sina | Optics lab | LOCAL | SPI work | Ongoing |
| 20:18 | TCS | Sophie | Prep lab | N | CHETA work | 21:03 |
| 20:21 | SUS | Oli | LVEA | N | Take picture of a rack | 20:25 |
| 20:32 | BHD | Elenna | Optics lab | LOCAL | BHSS work | Ongoing |
| 20:34 | PEM | RyanC | CER | N | Swap dm comms cables | 20:41 |
| 20:37 | SUS | Oli | Optics Lab | LOCAL | Working BHSS system | Ongoing |
| 20:40 | SQZ | Sheila | SQZT7 | N | Checking for people working at height to transition. | 21:02 |
| 20:41 | EE | Fill | CER | n | Grounding cables | Ongoing |
| 20:51 | VAC | Gerardo | LVEA | N | Take off turbopump | 21:02 |
| 21:01 | EE | Betsy, Marc, Tony | Vac Prep | N | Cable testing | Ongoing |
| 21:49 | OPS | Ibrahim | CER / Clean storage | N | C3 cloth covers checks | 22:18 |
| 22:35 | Calum | Vac Prep lab | N | Talk to Betsy | 23:20 | |
| 22:58 | VAC | Jordan | LVEA | N | Grab parts by HAM1 | 23:03 |