Displaying report 1-1 of 1.
Reports until 12:49, Wednesday 25 March 2026
H1 CDS (ISC, SPI, SUS)
filiberto.clara@LIGO.ORG - posted 12:49, Wednesday 25 March 2026 (89641)
SPI and JAC Cable Work

WP 13105
WP 13113

During the last two days CDS EE has completed the following:

  1. SPI Optical Fiber pulled from the PSL enclosure to SUS-R2
  2. Heliax cable pulled from ISC-C3 to SUS-R2, part of SPI
  3. Two Heliax cables pulled from ISC-C4 to ISC-R2, part of JAC
  4. Cabling disconnected to IOT1 and ISCT1

This completes dirty work over HAM1 and HAM2. In the next two weeks, will close out work in SUS-R2 before HAM3 is vented.

List of items needed for SUS-R2:

  1. Install power supplies in CER Mezzanine
  2. Terminate power cables and install junction box
  3. Terminate Heliax cable
  4. Test and install two SAT Amp Chassis
  5. Installation of DC sequencer
  6. Install QOSEM Sat Amp
  7. Pull cabling from SUS-R2 to HAM3
  8. Installation of SPI electronics

F. Clara, J. Kissel, J. Oberling, M. Pirello, T. Sanchez, and R. Thompson

Displaying report 1-1 of 1.