TITLE: 04/06 Day Shift: 1430-2330 UTC (0730-1630 PST), all times posted in UTC
STATE of H1: Planned Engineering
INCOMING OPERATOR: None
SHIFT SUMMARY:
GV2 was hard closed, one of HAM1's doors (-y) was installed (+y tomorrow).
Suite of CDS tasks were started in the afternoon (had issues with restoring SEIH7).
Please Ignore: "IMC INPUT POWER" Ops Overview (Jennie mentioned the calculation is not correct on this medm.)
LOG:
- 1454 PSL power taken from 10W to 0W
- 1513-1533 lvea prep for the week's activities (randy)
- 1550 CEBEX contractor on back-side of Y-arm to dig down to water line to get size of pipe (bubba)
- 1626-1650 MY to get info on genie lift batteries (chris)
- 1630-1750 looking for fil in lvea(marc)
- 1637-1655 tour for the new fellow (Madi) & put parts away (jennie)
- 1642-1827 unlocking HAM1 ISI (jim,tony)
- 1738 unlocked, jim running TFs, & tony OUT
- 2334 took HAM1 to ISI_DAMPED_HEPI_OFFLINE
- 1657-1715 Putting totes (betsy,mitch)
- 1703-1713 Grabbing dustmonitor in pcal lab (ryanC)
- 17041825 More lvea prep work (randy)
- 1720-1823 Hard Close gv2 & Filter Cavity gate valves (gerardo)
- 1729-1735 checking SPI cabling at CER & HAM3 (marc)
- 1759-1811 Tour (dolly)
- 1817 Checking TCS tables (camilla.madi)
- 1819-1829 cable checks (marc)
- 1859-1912 spi cabling at cer + lvea (jeff, fil)
- 1900 Locking up HAM3 HEPI (jim)
- 1900 HAM3 taken to ISI_OFFLINE_HEPI_ON
- 1913 SEI_HAM3 taken to OFFLINE (jim)
- 1946-2000 HAM1 door prep (randy)
- 2004-2320 SPI & bsc2 in-rack cabling at cer (fil)
- 1935-2010 installing cables in SEI-C1 rack
- 2015-2235 HAM1 door (randy, travis, gerardo)
- 2024 travis joining, 2029 gerardo joining
- -Y HAM1 door was installed. Then the cleanroom was moved so the +Y HAM1 door can be installed tomorrow.
- 2030-2150 CHeTA viewport inspection in optics lab (camilla, madi)
- 2043-2050 lvea walkabout: bsc platforms, laydown areas (betsy)
- 2150-2233 Another trip to lvea; also had group move a cleanroom (betsy and crew)
- 2047 cds model (susb13, sei7) work (jeff.dave.oli, erik)
- 2115 Erik & marc heading out to the floor to install new boards
- 2206 taking down seih7
- After this was brought back, had issues with the daq (could not ISOLARE HAM7). Erik's doing a power cycle of the crate, but still have the issue; looks like they have found a bug. Working on a workaround at the moment
- 2117 STS wiring in cer (jim)