H1 AOS
betsy.weaver@LIGO.ORG - posted 14:06, Monday 06 April 2026 (89792)
Ham1 closeout again, Trello Plan for next few weeks - BBSS vent start
Now that HAM1 is closing again (doors going on with VAC team now), we are turning attentions back to the CDS and BBSS work slated in line next.  Attached is the snapshot of the Trello with the next vent actions queued up.  We anticipate venting the corner chamber volume and also opening HAM3 this week.