betsy.weaver@LIGO.ORG - posted 14:13, Monday 06 April 2026 - last comment - 16:28, Monday 06 April 2026(89793)
BSC2 Cross Flow cleanroom and eMOD platform access
Randy has been hard at work adding temp handrails and the eMod garbing cleanroom to the BSC2 platform access area.  Its pretty workable now.  The temp handrails have a pretty large footprint so I might make changes to those in the next incarnation of this, so the walkway from the eMod to the BSC2 platform is pretty narrow.  This platform and eMod placement will service BSC1 and BSC3 as well however, so we will rework or remove some handrails as we add those sections.  The tent is easy to pull back when we need the dome and cartridge to be craned away.
Images attached to this report
Comments related to this report
corey.gray@LIGO.ORG - 16:28, Monday 06 April 2026 (89795)EPO

tagging for EPO photos