LHO General
ryan.short@LIGO.ORG - posted 16:46, Thursday 23 April 2026 (89990)
Ops Day Shift Summary

TITLE: 04/23 Day Shift: 1430-2330 UTC (0730-1630 PST), all times posted in UTC
STATE of H1: Planned Engineering
INCOMING OPERATOR: None
SHIFT SUMMARY: The soon-to-be-removed beamsplitter is now covered in the chamber with cables disconnected, baffles removed, and keel masses off the top of the ISI. The old "meat locker" was also craned over the X-arm and is staged at the LVEA hi-bay door.
LOG:

Start Time System Name Location Lazer_Haz Task Time End
14:36 FAC Kim, Nellie LVEA - Technical cleaning 15:52
15:05 FAC Randy LVEA - BSC2 mass craning 16:53
15:07 FAC Mitch LVEA - BSC2 mass craning 16:35
16:08 FAC Nellie LVEA - Technical cleaning 16:46
16:10 FAC Kim LVEA - Technical cleaning 16:46
16:28 PEM Ryan C CER - Dropping off dust monitor 16:30
16:46 FAC Kim, Nellie EY - Dropping off garb 17:26
17:08 PROP Christina MY, MX - Looking for a crate 17:28
17:26 IAS Jason LVEA - Staging equipment for FARO 19:15
17:32 IAS Ryan C LVEA - Staging equipment for FARO 19:15
18:05 SUS Ibrahim, Tony LVEA - Baffle/cable removal on BS, prep for cartridge 19:39
18:19 SUS Betsy LVEA - Baffle/cable removal on BS, prep for cartridge 19:39
18:26 TCS TJ LVEA - Dropping off parts and looking for tubing 18:39
19:54 FAC Jordan, Randy LVEA - Craning meatlocker 20:46
20:07 SUS Ibrahim LVEA - Dropping off parts 20:21
20:25 IAS Jason, Ryan C LVEA - FARO in West bay Ongoing
20:29 TCS Camilla, Madi EX YES HWS table alignment 22:54
20:42 SUS Ibrahim LVEA - BS SUS de-cabling 23:25
20:43 SUS Tony LVEA - BS SUS de-cabling 23:25
20:49 SUS Betsy LVEA - BS SUS de-cabling 23:24
21:03 ISC Keita, Elenna, Disha OptLab - BHD work 22:57
21:28 TCS TJ LVEA - Measure a tube on TCSX 21:42
22:42 SEI Patrick MER - Imaging HEPI pump controller computer 23:04
23:32 ISC Camilla LVEA - IOT2L bellows Ongoing