Displaying report 1-1 of 1.
Reports until 08:08, Friday 24 April 2026
H1 General
anthony.sanchez@LIGO.ORG - posted 08:08, Friday 24 April 2026 (89995)
Friday morning Ops shift report.

TITLE: 04/24 Day Shift: 1430-2330 UTC (0730-1630 PST), all times posted in UTC
STATE of H1: Planned Engineering
OUTGOING OPERATOR: None
CURRENT ENVIRONMENT:
    SEI_ENV state: MAINTENANCE
    Wind: 9mph Gusts, 5mph 3min avg
    Primary useism: 0.01 μm/s
    Secondary useism: 0.14 μm/s 
QUICK SUMMARY:
H1's corner station is still still vented for Beam splitter upgrades. Lots of activities in BSC1 & 2 chamber.

Potential work today:
More prep work for flying out the BS cartridge. 
SEI - HEPI CS pump station troubelshoot (Jim)?
Reconnect IOT1 (Tony, Camilla, Jennie, Fil cable?)  this table is back in place and bellows are in place.
End Station HWS work (Camilla, Maddi, TJ)
CDS/EE - LVEA, MER cabling for HAM6 A+,  work at SUS-M2, SEI-M1, and SUS-R7. [HAM7 sus to SAFE]
BSC2 - Drop Elliptical Baffles  <-( I think this is done already) 
VAC - CP1 Regen, lots of activity at Y-Manifold in LVEA, a few weeks

Displaying report 1-1 of 1.