Reports until 16:05, Wednesday 18 December 2013
corey.gray@LIGO.ORG -
posted 16:05, Wednesday 18 December 2013 (9000)
Today's Activities:
-
Disabling Capacitive Position Sensors (CPS's) for ITMx & ITMy ISI's for a noise test for master & beating (Hugh, Jim, Fabrice)
-
Cheryl working on PSL today (along with Sheila)
-
LVEA Commissioning crew: working on cameras in the morning
-
HTTS Model work continues (Dave, Jim, Jeff)
-
Landry & Kai scoping shots along X1 Beam Tube
-
Inductive Position Sensor (IPS) work on ITMX HEPI (Hugh, Jim, Fabrice)
-
Removing Demod Board from AS Rack (Jamie)
-
PSL Beckoff work (Daniel)
-
Dave/Jim B working in CER
-
Pump carts connected to GV7 (LVEA) & GV20 (EX) by Kyle
-
Network cable being pulled at EX (Filiberto/Aaron)
-
SR SUS staging work (Jeff/Andres)
-
Filiberto needed to run some cables around HAM3 (notified Kiwamu of his rumblings)