kyle.ryan@LIGO.ORG - posted 16:40, Wednesday 18 December 2013 (9012)
Misc. prep steps for opening CS to X-end
Today I "burped" GV7 and GV20's unpumped gate annulus volumes into aux. pump carts -> I also valved-in IP12 and IP5 (I had originally tried IP6 before IP5 but it didn't step its HV and had minimal net pump speed with its fixed HV value - I'll need to change IP6's controller settings to operate in "step" mode) -> If we do end up opening up the CS and X-end to the BT, I'll valve-out the respective turbos such that no rotating pumps are valved-in while the BT is exposed.