SHIFT SUMMARY: Both doors are now off of HAM2 and the ISI is locked. The new BBS has also been delivered and is being prepped near the test stand. Baffle installation in HAM3 continueds today as well, and the TCSY table water lines started to be replaced.
LOG:

Start Time System Name Location Lazer_Haz Task Time End
14:54 VAC Jordan LVEA - Checking pumps (CP1) 15:02
15:14 FAC Kim LVEA - Technical cleaning 16:45
15:33 EE Fil MY - Picking up cables 16:03
15:40 FAC Randy LVEA - Prep for HAM2 door removal 16:08
16:00 SPI Jeff Opt Lab - Part spelunking 16:08
16:02 IAS Jason, Stephen LVEA - BS FARO surveying 18:59
16:08 VAC Gerardo, Jordan, Randy LVEA - HAM2 door removal 18:43
16:09 PEM Robert LVEA - HAM3 baffle installation 19:13
16:16 IAS Ryan C LVEA - BS FARO surveying 18:59
16:19 CAL Tony, Dripta PCal Lab - Prepping for measurement 16:45
16:26 PEM Mitchell LVEA - HAM3 baffle installation 19:25
16:46 CAL Tony, Dripta EX YES PCal measurement 18:49
16:50 FAC Chris LVEA - FAMIS checks 17:23
17:01 EE Fil MER - BHD electronics cabling 18:39
17:24 FAC Chris Ends, Mids - FAMIS checks 18:37
17:25 FAC Kim LVEA - Technical cleaning 18:13
17:27 VAC Travis LVEA - HAM2 door removal 18:44
17:37 SUS Betsy, Ibrahim LVEA - Many tasks (Betsy out @ 18:22) 18:37
18:13 FAC Kim FCES - Technical cleaning 18:59
18:23 SUS Betsy EX - Looking for ergo arm part 19:06
18:43 SEI Jim LVEA - Locking HAM2 ISI 19:06
19:18 FAC Randy LVEA - Craning in West bay 20:03
20:14 VAC Jordan LVEA - HAM6 RGA 20:23
20:15 FAC Randy LVEA - Moving scaffolding, BBS staging 22:13
20:15 SUS Betsy LVEA - BBS staging Ongoing
20:19 IAS Jason, Ryan C, Stephen LVEA - BS FARO surveying Ongoing
20:33 SUS Ibrahim LVEA - BBS staging Ongoing
20:36 SAF Richard LVEA - Checks 21:09
20:39 CAL Tony PCal Lab - Checking part number 21:30
20:52 SEI Jim LVEA - HAM3 table masses 22:37
20:59 TCS TJ, Camilla, Madi LVEA - TCSY table water lines 23:30
22:07 SUS Tom LVEA - Delivering cables 22:13
22:10 VAC Jordan LVEA - HAM6 RGA 22:18
22:47 SLIC Robert LVEA - HAM3 baffle installation Ongoing
22:55 VAC Jordan, Gerardo LVEA - Bringing pump to CP1 23:50
Displaying report 1-1 of 1.