ryan.short@LIGO.ORG - posted 07:42, Friday 15 May 2026 (90252)
Ops Day Shift Start

TITLE: 05/15 Day Shift: 1430-2330 UTC (0730-1630 PST), all times posted in UTC
STATE of H1: Planned Engineering
OUTGOING OPERATOR: None
CURRENT ENVIRONMENT:
    SEI_ENV state: MAINTENANCE
    Wind: 6mph Gusts, 3mph 3min avg
    Primary useism: 0.06 μm/s
    Secondary useism: 0.13 μm/s 
QUICK SUMMARY: Work in HAM2 continues today as part of the ISS swap, but not until the Kobelco unit has had some maintenance done this morning. No in-chamber work allowed until that's finished. 31 disconnected channels on the EDC since the corner HEPI pump controller appears to still be down.

In other news, a M6.7 EQ out of Japan is rolling through, and it's a beautiful morning on-site.