Ibrahim, Betsy, Oli
Today, we installed BBS01 into the BBSS successfully.
BBS01 was on a table. BBSS was on the aluma lift. We picked BBS01 using the ERGO arm and slowly came into the optic. In this process, we:
On top of pictures below, 2 videos:
Wahoo! Congrats, y'all!
Note, current status as of last Thur was handoff to FARO IAS (Jason/Ryan C) who are up for mapping and guiding us into place. CAD files from CIT arrived Thur so quite literally just in time to get on it.
Also, thanks Travis for all the pictures.