LHO General
ryan.short@LIGO.ORG - posted 16:32, Tuesday 19 May 2026 (90284)
Ops Day Shift Summary

TITLE: 05/19 Day Shift: 1430-2330 UTC (0730-1630 PST), all times posted in UTC
STATE of H1: Planned Engineering
INCOMING OPERATOR: None
SHIFT SUMMARY: More alignment work in HAM2 and BBSS alignment today. Now that the LVEA is back to Laser SAFE, more alignment steps for the BBSS and prep for the GV7 repair can be done starting tomorrow. The SPI NPRO continues to run overnight in the optics lab with proper curtains and signage in place.
LOG:

Start Time System Name Location Lazer_Haz Task Time End
19:43 SAF LASER HAZARD LVEA YES LVEA IS LASER HAZARD 23:11
14:43 FAC Kim LVEA - Technical cleaning 16:15
15:37 SUS Betsy LVEA - Looking for parts 15:51
15:49 VAC Jordan LVEA - Pump checks 15:56
15:49 SUS Ibrahim LVEA - BBSS staging 19:32
16:20 SUS Betsy LVEA - BBSS staging 17:47
16:30 PEM Ryan C LVEA - Setting up DM at test stand 16:46
16:34 FAC Kim LVEA - Technical cleaning 17:21
17:41 VAC Jordan +1 EX, MX, EY, MY - N2 tank inspections 20:22
17:52 SUS Betsy LVEA - BBSS staging 19:33
18:31 SUS Oli LVEA/Opt Lab - Grabbing parts and delivering 19:29
19:29 SPI Josh LVEA - Checking cable 19:37
20:26 VAC Travis LVEA - HAM3 feedthrus 21:23
20:28 SUS Betsy LVEA - BBSS work 22:48
20:29 IAS Jason, Ryan C LVEA - BBSS surveying setup 22:48
20:33 SUS Corey Opt/Prep Labs - Looking for parts 20:58
20:35 SEI Jim LVEA - HAM3 feedthrus 21:24
20:46 SAF Richard LVEA - Safety checks 21:15
20:48 ISC Keita LVEA Y HAM2 beam alignment 22:53
20:52 ISC Elenna LVEA Y HAM2 beam alignment 22:53
20:54 SEI Shoshana LVEA - HAM3 feedthrus 21:24
21:06 SPI Jeff Opt Lab Local SPI alignment (working late) Ongoing
21:18 EE Fil MER - HEPI electronics 23:18
21:33 CAL Tony PCal Lab Local Set up measurement 22:32
21:33 SUS Ibrahim LVEA - BBSS work 22:35
22:21 SEI Jim LVEA - Getting boxes from H2 PSL 22:27
22:58 SAF Oli LVEA - Transitioning to Laser SAFE 23:10