H1 INS
jodi.fauver@LIGO.ORG - posted 12:22, Thursday 19 December 2013 (9029)
Prep Work for 2014 activities in LVEA West Bay
After discussions yesterday, we agreed on a plan for cleanroom usage for upcoming work in the LVEA. The work includes, but is not limited to, ACB/CPB/OFI assembly and ITM swaps. The easiest solution seemed to be clustering the work in the West Bay. We will add a Work Space cleanroom and a garbing/staging cleanroom to the four existing cleanrooms. (Please see the attached sketch for details.) Apollo will move the additional cleanrooms as soon as they get a chance.