TITLE: 06/01 Day Shift: 1430-2330 UTC (0730-1630 PST), all times posted in UTC
STATE of H1: Planned Engineering
INCOMING OPERATOR: None
SHIFT SUMMARY: Very busy day with lots of visitors on site! Essentially everything was recovered following the weekend power outage, doors on HAM7 were removed and SQZ work in the chamber started after the ISI was locked, QOSEM work continued on the BBSS, the ISI was balanced on the test stand, prep began for the ITM cage baffle installation, GV7 was cycled and left closed for venting of the X-manifold, more beam alignment went on in HAMs 2 and 3, turbopumps at EY and MY were tested, FARO surveying began in HAM3, CRS building continued, and SPI work in the optics lab is ongoing. The EDC is still showing several disconnected channels, some of which relate to EY dust monitors.
LOG:
| Start Time | System | Name | Location | Lazer_Haz | Task | Time End |
|---|---|---|---|---|---|---|
| 19:29 | SAF | Laser HAZARD | LVEA | YES | LVEA is Laser HAZARD | 17:21 |
| 14:36 | FAC | Kim | LVEA | - | Technical cleaning | 17:01 |
| 14:43 | FAC | Randy | LVEA | - | Prep for HAM7 doors | 15:12 |
| 15:01 | VAC | Jordan | LVEA | - | Checking pumps | 15:10 |
| 15:37 | SPI | Jeff | Opt Lab | Local | Turning on laser | 17:00 |
| 15:38 | IAS | Ryan C | LVEA | - | Checking on FARO | 15:47 |
| 15:46 | ISC | Keita | LVEA | - | Opening light pipe | 15:48 |
| 15:46 | VAC | Jordan | MY, EY | - | Turbopump checks | 16:40 |
| 16:04 | PSL | Jason | LVEA | - | Powering on PSL CB2 | 16:22 |
| 16:19 | VAC | Travis | Lvea | - | HAM7 door prep | 16:25 |
| 16:28 | SAF | Ibrahim | LVEA | - | Transition to SAFE | 17:21 |
| 16:54 | SUS | Oli, Tom | LVEA | - | BBSS QOSEM | 18:19 |
| 17:21 | SUS | Ibrahim | LVEA | - | BBSS work | 18:19 |
| 17:22 | FAC | Randy | LVEA | - | HAM7 door removal | 19:22 |
| 17:22 | VAC | Travis, Jordan | LVEA | - | HAM7 door removal | 18:40 |
| 17:22 | FAC | Kim | EX, EY | - | Technical cleaning | 18:19 |
| 17:24 | CDS | Erik | EY, EX | - | Power outage recovery | 18:27 |
| 17:29 | VAC | Gerardo | LVEA | - | HAM7 door removal | 18:41 |
| 17:33 | SLiC | Mitch, Anamaria | LVEA | - | Baffle install planning | 17:46 |
| 17:38 | SPI | Corey | Opt Lab | - | Optic cleaning | 19:46 |
| 18:15 | IAS | Jason, Ryan C | LVEA | - | FARO surveying HAM3 | 20:33 |
| 19:04 | SAF | Sheila | LVEA | YES | Transition to Laser HAZARD | 19:26 |
| 19:09 | TCS | Camilla | MER | - | Turning on TCS chillers | 19:25 |
| 19:26 | SAF | Laser HAZARD | LVEA | YES | LVEA is Laser HAZARD | Ongoing |
| 19:27 | SEI | Shoshana, Arnaud | H2 PSL | - | CRS builds | 19:53 |
| 19:34 | SEI | Jim | LVEA | - | Locking HAM7 ISI | 19:54 |
| 19:55 | SEI | Jim | EX, EY | - | Bringing up HEPI | 20:33 |
| 20:13 | SPI | Jeff, Sina | Opt Lab | Local | SPI alignment | 22:04 |
| 20:24 | VAC | Jordan, Jake, Owen | EY, MY | - | Shutting down turbopumps | 21:20 |
| 20:33 | ISC | Marc, Keita | CER | - | PZT power supply | 20:37 |
| 20:50 | SLiC | Betsy, Anamaria | LVEA | - | Staging for baffle install (Anamaria out @ 23:04) | Ongoing |
| 20:59 | SEI | Jim, Ibrahim | LVEA | - | BBSS ISI balancing | Ongoing |
| 21:08 | VAC | Travis, Gerardo | LVEA | - | X-man vent and open GV2 (Gerardo out @ 23:03) | Ongoing |
| 21:24 | VAC | Jordan, Jake, Owen | LVEA | - | X-man vent and open GV2 | 22:18 |
| 21:28 | SEI | Marc, Patrick | MER | - | HEPI electronics | 21:58 |
| 21:30 | SQZ | Sheila, Camilla | LVEA | Y | HAM7 SQZ beam hunting (Camilla out @ 22:58) | Ongoing |
| 21:38 | IAS | Jason, Ryan C | LVEA | - | FARO surveying HAM3 | Ongoing |
| 21:58 | ISC | Keita, Rahul, Disha | LVEA | Y | HAM2/3 beam alignment | Ongoing |
| 22:04 | SEI | Arnaud, Shoshana, Alex | H2 PSL | - | CRS builds (Alex out @ 23:11) | Ongoing |
| 22:32 | VAC | Jordan, Jake, Owen | LVEA | - | Venting X-manifold | Ongoing |
| 22:35 | SPI | Jeff, Sina | Opt Lab | Local | SPI alignment (Jeff out @ 23:05) | Ongoing |
| 23:18 | AOS | Mitchell | LVEA | - | Delivering garb | Ongoing |