H1 General
jeffrey.bartlett@LIGO.ORG - posted 16:07, Friday 20 December 2013 (9051)
Ops Summary

LVEA Laser Hazard

Apollo Installing TCS plumbing in the LVEA
SEI group Running HEPI transfer functions   

09:00 Richard remove yellow view port cover on X-Arm spool to check ACB photo diodes 
09:10 Andres in LVEA working on H1-SR2
10:22 Corey going to End-Y to recover camera equipment
10:30 Richard open gate due to snow and slick roads
10:37 Kiwamu Working on IOT2L in LVEA
10:51 EE interns pulling cables around HAM2
11:00 Cheryl & Kiwamu Open HAM2 East side view ports, with ALS pipe closed, to look at in chamber optics 
11:02 Filiberto working on diodes at the BSC3 SUS rack	