Today:
- Jim, Mitchell, and Randy reinstalled the Keel payload (craning it into place up on top of the ISI.
- Jim dropped all 40 cables down from the ISI to the chamber. He also worked on cabling up the ISI to tidy and add the new stuff more appropriately.
- Tony and Oli embarked on plugging everything back in oer the serial number map in the google doc on D1003079. They left the white CPS cables for Jim to do.
- Jason and RyanC took the first round of BBSS structure (/ISI) shots, see their alog. Promising, corroborative results.
- Travis and I reinstalled the Stays and the last Vibration Absorber onto the BBSS structure and re-tightened everything.
- Oli, FIl and I plugged in the Top stage QOSEM cables at the Satellite box, then embarked on a small cable re-understanding regarding M2 and M3. Fil will move the M2 stage Sat box from R4 to R2 (we had been still needing it there while on the test stand) in the coming day(s). The QOSEMs seem to have signal in the right places.
Up next:
Start HEPI spring loading, recheck FARO shots, move per what FARO says we need to move
Suspend the BBSS, take Top TFs, then work on M2 and M3 stage OSEMs.