Mitch, Jim
This morning Mitch and I went to HAM2 and unlocked the table to work on rebalancing the ISI. Table is rebalanced now, RX/RY locked unlocked shifts are around 10urad, RZ was a little bigger at ~15urad. I have not had a chance to do close out tfs.
After that was done, we tried to install the vertical L4Cs but were missing the hardware for the dog clamps. Found some class A stuff in the staging building that works, but when I went to install them to finish, I found one of the helicoils for the V3 L4C was missing. Rahul had some in the triples lab, so I will try to find time to install that tomorrow. The other 2 vertical L4Cs are done though, so the in vac portion of that install is mostly finished.