TITLE: 06/26 Day Shift: 1430-2330 UTC (0730-1630 PST), all times posted in UTC
STATE of H1: Planned Engineering
OUTGOING OPERATOR: None
CURRENT ENVIRONMENT:
SEI_ENV state: MAINTENANCE
Wind: 17mph Gusts, 12mph 3min avg
Primary useism: 0.02 μm/s
Secondary useism: 0.08 μm/s
QUICK SUMMARY:
- Cooler, breezy & cloudy morning; there was a M6.5 EQ a few hours ago in Philippines. DetChar meeting formally ended yesterday (so not leaving kitchen door unlocked).
- Due to RDO Fri, SQZ work may be a primary activity for the day. There is a plan to run measurements with the purge air turned off today (which would mean NO in-chamber work).
- Local laser hazard in East Bay continues for SQZ HAM7 work (rest of LVEA is laser SAFE except for at height).
- CPS work continues (I know this because Verbal Alarms is overtaken by the "HAM3 CPS Glitch" every few seconds.)
- Assume BSC2 HEPI actuator work is also ongoing into next week
- HAM3 Baffling is also still ongoing (baffles in-chamber, but still need final positioning, when allowed--BBSS prevented this Thurs).
- Other ongoing work: CRS, SPI, EX electrical ground studies, B&K work in-chamber work, and possibly close-out & seal-up chambers next week(?)
Coming down to the final weeks of closeout on this vent window.